top of page
Search

Property Development Delays: The Cost of Doing Nothing and How It Eats Away at Your Profit

Writer: Adam Bahrami
Adam Bahrami
24 minutes ago
9 min read

Property developers will often spend weeks negotiating a reduction in the purchase price of a development site, comparing construction quotations and reviewing consultant fees. Yet some allow their projects to sit idle for months without properly considering the financial consequences.


A successful development isn't simply about buying well, building within budget and achieving strong selling prices. It's also about managing the time between those milestones.


Property development delays can turn an attractive investment into a marginal project. Interest continues accumulating, ownership expenses remain payable, construction prices may increase, and market conditions can change.


The developer is spending more money without necessarily creating any additional value.


Whether you're undertaking your first duplex or managing multiple residential developments, understanding the financial value of time is essential to protecting your development profit.


Why Time Matters in Property Development Feasibility


Every development feasibility relies on four fundamental assumptions: acquisition costs, development expenditure, anticipated revenue and project duration.


Of these, time is often the least actively managed.


A developer might prepare a detailed construction budget but allow a relatively arbitrary timeframe for planning approvals, construction and settlement.


What happens if a 24-month development takes 30 months? What if construction commencement is delayed because of unresolved development consent conditions?


Each of these circumstances changes the financial outcome.


A development programme should therefore be prepared alongside the feasibility, connecting anticipated expenditure, finance requirements and revenue to realistic project milestones.



How Much Do Property Development Delays Cost?


Consider a developer who purchases a residential development site in Sydney with a $2.5 million acquisition loan at an illustrative annual interest rate of 9%.


Before construction even begins, the developer is paying approximately $18,750 per month in interest.


Additional delay

Additional interest

1 month

$18,750

3 months

$56,250

6 months

$112,500

9 months

$168,750

12 months

$225,000


Now add Council rates, applicable land tax, insurance, maintenance, additional consultant fees and potential construction cost increases.


The combined financial impact of a six-month delay could exceed $200,000.


This is why a seemingly inexpensive property with a complicated development approval pathway may ultimately cost more to develop than a higher-priced site with fewer constraints.


Interest calculations assume a constant outstanding loan balance and exclude compounding and additional facility charges.


Not Every Month of Delay Costs the Same


A common mistake in development feasibility is calculating interest on the entire project budget for the full development period.


Construction finance is generally drawn progressively as building works advance. Consequently, the outstanding debt increases throughout construction, potentially making delays more expensive towards completion.


Development stage

Outstanding debt

Monthly interest at 9%

Planning and approvals

$1,500,000

$11,250

Early construction

$2,250,000

$16,875

Mid-construction

$3,000,000

$22,500

Approaching completion

$4,500,000

$33,750


A three-month delay during planning could cost approximately $33,750 in interest. The same delay towards construction completion could cost $101,250.


A properly prepared development cash flow should account for progressive loan drawdowns, equity contributions, interest capitalisation, facility fees and anticipated debt repayments.


Developers should also separate finance expenses from recurring property ownership costs to avoid overlooking or double-counting expenditure.


How Six Months Can Change Your Development Profit


Consider a hypothetical townhouse development with an anticipated gross realisation value (GRV) of $7.5 million.


The original feasibility indicates a healthy profit. However, approval complications and delays in commencing construction extend the development programme by six months.

A three-month delay during planning could cost approximately $33,750 in interest. The same delay towards construction completion could cost $101,250.


A properly prepared development cash flow should account for progressive loan drawdowns, equity contributions, interest capitalisation, facility fees and anticipated debt repayments.


Developers should also separate finance expenses from recurring property ownership costs to avoid overlooking or double-counting expenditure.



How Six Months Can Change Your Development Profit


Consider a hypothetical townhouse development with an anticipated gross realisation value (GRV) of $7.5 million.


The original feasibility indicates a healthy profit. However, approval complications and delays in commencing construction extend the development programme by six months.


Feasibility item

Original forecast

Revised forecast

Gross realisation

$7,500,000

$7,500,000

Original development costs

$6,200,000

$6,200,000

Additional interest

—

$112,500

Additional holding costs

—

$25,000

Construction escalation

—

$80,000

Additional consultant fees

—

$15,000

Total development cost

$6,200,000

$6,432,500

Development profit

$1,300,000

$1,067,500

Profit on cost

21.0%

16.6%


The additional six months have reduced the projected development profit by $232,500, representing almost 18% of the original anticipated return.


Now suppose the residential market softens during this period and the completed properties sell for 5% less than originally forecast.


The remaining profit falls to $692,500.


Almost 47% of the original development profit has disappeared.


The developer is still delivering the same townhouses. The financial circumstances surrounding the project have simply changed over time.


This is why development feasibility should be regularly updated rather than treated as a document prepared solely to justify the original acquisition.


Figures are hypothetical and exclude detailed GST and income tax calculations.


What Causes Property Development Delays? 


While some delays are unavoidable, others result from matters that could have been identified or managed earlier.

Inadequate Due Diligence

A site may satisfy the relevant planning controls yet require complicated stormwater arrangements, additional easements, infrastructure upgrades or substantial excavation.


Discovering these issues after settlement exposes the developer to unexpected expenditure and potentially months of additional holding costs.


Understanding development constraints before acquisition can influence the purchase price, development strategy and decision to proceed.


Poor Consultant Coordination

Engaging experienced architects, engineers and town planners does not automatically guarantee an efficient development process.


An architectural design may require substantial amendments following advice from the civil engineer. Those amendments may subsequently affect structural engineering, landscaping and construction costs.


Before long, several consultants are revising documentation that has already been completed and paid for.


Someone needs to coordinate these disciplines and understand how their decisions affect the entire development.


Underestimating the Period Between DA and CC Approval

Receiving development approval doesn't necessarily mean a project is ready for construction.


In NSW, development consent conditions, engineering documentation, Construction Certificate requirements and service authority approvals may remain outstanding.


Where commercially appropriate, some of these requirements can be investigated or progressed during the planning process, subject to the remaining approval risks.


Delayed Decisions

Sometimes the developer becomes the reason the project isn't progressing.


A consultant is waiting for instructions, a design amendment requires approval, or a quotation remains under consideration.


For a development incurring $25,000 per month in finance and holding expenses, two weeks of avoidable critical-path delay could cost approximately $11,500.


The financial consequences of postponing a decision should be considered alongside the decision itself.



When Saving Money on Consultants Becomes Expensive


Consider two equally capable engineering consultants quoting for the same scope of work.



Consultant A

Consultant B

Professional fee

$8,000

$12,000

Delivery timeframe

8 weeks

3 weeks


Appointing Consultant A appears to save $4,000.


However, if the engineering documentation is on the critical path and the development is incurring $20,000 per month in carrying costs, the additional five weeks could cost approximately $23,000.


The cheaper consultant could ultimately increase the total development expenditure by $19,000.


This doesn't mean developers should automatically appoint the fastest or most expensive consultant.


Quality, competence, scope and reliability remain essential. However, delivery timeframes deserve greater consideration when evaluating quotations.


The lowest individual price doesn't always produce the lowest development cost.


Critical Path Management in Property Development


A development programme should identify the activities that determine the earliest achievable completion date. This is known as the critical path.


For a residential development, critical activities may include:

  • Planning and development approval.

  • Detailed engineering and consent conditions.

  • Construction certification and procurement.

  • Construction and infrastructure works.

  • Occupation Certificates and subdivision registration.

  • Purchaser settlements and finance repayment.


Some activities can run concurrently, while others depend entirely on preceding tasks.


There is little commercial benefit in accelerating landscaping documentation if an unresolved drainage approval is preventing construction from commencing.


Effective development management involves understanding these dependencies and prioritising the activities that genuinely move the project forward.


Does a Fixed-Price Building Contract Protect Against Delays?


Fixed-price construction contracts and Guaranteed Maximum Price (GMP) arrangements can help manage certain construction expenditure risks.


However, they do not automatically protect developers against programme delays.


Variations, latent conditions, adverse weather and other circumstances may entitle the builder to Extensions of Time, depending on the contract.


Liquidated damages may provide a contractual remedy for certain delays attributable to the builder, but they may not cover all additional finance costs or lost opportunities.


Developers should assess the builder's programme, resources, construction methodology and delivery capabilities alongside the contract price.


Proper contract administration and early identification of construction delays can be more valuable than attempting to recover their financial consequences afterwards.



Holding Costs Don't Stop at Practical Completion


One of the more expensive stages of development can occur after construction is substantially completed.


The developer may still be waiting for an Occupation Certificate, subdivision registration, service authority clearances or purchaser settlements.


Meanwhile, most construction finance may already have been drawn, meaning interest exposure could be close to its highest level.


A development feasibility should therefore extend beyond Practical Completion to include certification, settlement, debt repayment and, where applicable, refinancing.


The financial finish line isn't necessarily the day the builder hands over the keys.


Capitalised Interest and Tax Benefits Don't Make Delays Free


Capitalising interest can assist developers with cash flow by reducing the need to make monthly interest payments.


However, the interest remains a development expense and may increase the outstanding loan balance.


Similarly, potential tax deductions associated with holding expenses should not be treated as guaranteed savings.


Australian taxation rules, including vacant land deduction restrictions, can affect the treatment of these expenses depending on the ownership structure and purpose of the development.


Developers should obtain project-specific accounting advice before incorporating potential tax benefits into their feasibility.


A development should make commercial sense without relying on uncertain tax advantages.


Development Profit Versus Return on Equity


The financial consequences of development delays extend beyond direct expenses.


Consider two developments, each requiring $1 million in equity and delivering $400,000 in profit.



Project A

Project B

Equity invested

$1,000,000

$1,000,000

Development profit

$400,000

$400,000

Project duration

18 months

36 months

Return on equity

40%

40%

Simple annualised return

26.7%

13.3%


Both projects generate the same profit, but Project A releases the developer's capital 18 months earlier.


For boutique developers with limited access to capital, this can determine how quickly they undertake another development and grow their business.


Experienced developers assess not only the total profit but also the time required to achieve it, the capital invested and, where appropriate, the Internal Rate of Return (IRR).



Seven Ways to Reduce Property Development Delays


While delays cannot always be prevented, developers can reduce their exposure through disciplined management.


  1. Conduct thorough due diligence. Identify planning, engineering and construction constraints before committing to a site.

  2. Prepare a realistic cash flow forecast. Model progressive expenditure, loan drawdowns and anticipated settlements.

  3. Establish a critical-path programme. Prioritise the activities that determine the development's completion date.

  4. Assign responsibilities and deadlines. Ensure every outstanding task has an accountable person and an agreed delivery date.

  5. Evaluate procurement decisions commercially. Consider scope, quality, delivery timeframe and overall project cost

  6. Regularly update your feasibility. Replace outdated assumptions with actual expenditure, current quotations and revised completion dates.

  7. Stress-test your development. Assess whether the project remains viable with an additional three, six or twelve months, higher interest rates or lower selling prices.


The objective isn't to rush development decisions or compromise construction quality. It is to prevent unnecessary delays from consuming the anticipated development profit.


OwnerDeveloper's Perspective: Being Busy Doesn't Mean Making Progress


Throughout our experience in building and property development, we've observed that a project can appear extremely busy without actually moving forward.


Consultants are engaged, meetings take place, emails are exchanged and invoices are paid.


But are the critical issues being resolved?


At OwnerDeveloper, we approach development management from the perspective of protecting the developer's investment.


When evaluating a decision, we consider what it will cost, how long it will take and how it will affect the overall commercial outcome.


Sometimes spending additional money upfront to resolve an issue can save considerably more than the initial expenditure. Other times, the responsible decision is to reconsider a design, change the development strategy or recognise that the project is no longer commercially viable.


Effective development management requires understanding the relationship between planning, construction, finance and time.



Collage of builders, couples, and home images with award badges; text reads From Planning & Approvals to Real Outcomes.

Frequently Asked Questions


How do property development delays affect profitability?

Delays increase exposure to finance expenses, holding costs, construction escalation and changing market conditions, potentially reducing the anticipated development margin.


How should developers calculate finance costs?

Finance costs should be modelled against anticipated outstanding debt throughout the development, incorporating progressive drawdowns, repayments and applicable facility terms.


What is the critical path in property development?

The critical path is the sequence of dependent activities that determines the earliest achievable project completion date.


Can a development manager reduce holding costs?

Effective development management can help reduce avoidable delays through consultant coordination, programme monitoring, procurement planning and timely decision-making.


Disclaimer: OwnerDeveloper’s blogs are provided for general information and educational purposes only. They do not constitute financial, legal, tax, investment or other professional advice. Every property development involves unique circumstances and risks. Readers should seek independent advice from appropriately qualified professionals before making any investment, financial or development decision.



 
 
 

2 Comments

Rated 0 out of 5 stars.
No ratings yet

Add a rating
Guest
5 minutes ago
Rated 5 out of 5 stars.

That example of losing nearly half the anticipated profit with a six-month delay and a 5% drop in sales prices really puts things into perspective.

Like

Guest
6 minutes ago
Rated 5 out of 5 stars.

Everyone talks about buying well, but very few talk about the cost of sitting on a site for 12 months waiting for approvals. Good article.

Like
_M4_1154_1224x816_2664142.jpg

Get Daily Updates

Sign up for exclusive insights, expert opinions, project showcases, and the latest industry news!

Thanks for submitting!

bottom of page