Getting a Development Application approved is a major step in any property development.


You've invested in architectural drawings, planning advice, consultant reports and the approval process. The proposed townhouses or duplex have received consent, and you're one step closer to construction.


But here's something developers need to understand.


An approved design isn't necessarily a construction-ready design.


The drawings that satisfy Council may not contain the technical information needed to price and build the project accurately.


And once detailed engineering begins, you might discover that the approved layout requires more excavation, structural work or drainage infrastructure than you originally allowed for.


The development may still be achievable.


The question is whether it's still commercially viable.


That's why good property development design should address planning approval, construction requirements and financial feasibility together, rather than treating them as separate exercises.


What Is the Difference Between Designing for Approval and Designing for Construction?


Designing for approval establishes what can be developed on a particular site under the applicable planning controls.


For a townhouse development in NSW, the assessment may consider building height, setbacks, floor space ratio, landscaping, overshadowing, privacy, access and neighbourhood impacts.


The Development Application drawings communicate the proposed layout, building form and relationship with the surrounding properties.


Designing for construction takes that approved proposal and develops the technical information needed to build it.


This includes structural engineering, civil works, drainage, building services, waterproofing details, materials and specifications.


The difference is important.


A planning-compliant design may still involve construction methods that are difficult, expensive or inefficient.


For developers, the objective shouldn't simply be to obtain the maximum allowable dwelling yield.


It should be to achieve an approved development that can be constructed efficiently and produce an acceptable financial return.


DA Drawings vs Construction Drawings: What Does Each Set Include?


Development Application drawings generally show the building's location, dimensions, floor layouts, elevations, external appearance and proposed levels.


They allow the consent authority to assess the development against the relevant planning requirements.


Depending on the site and proposal, the DA may also require landscape plans, stormwater information, shadow diagrams and specialist reports.


Construction drawings provide a more detailed description of the building.


They typically include architectural construction details, structural drawings, civil and hydraulic engineering, schedules and specifications appropriate to the project.


Consider a townhouse with a first-floor balcony.


The DA drawings may establish its position, dimensions and appearance.


The construction documentation needs to address the supporting structure, waterproofing, drainage, door thresholds, balustrade connections and interfaces with adjoining building elements.


Those details matter because the builder needs clear information to construct the work correctly.


Where details are missing or inconsistent, the builder may need to seek clarification, make pricing assumptions or request additional instructions.


That can affect construction cost and programme.



Why Buildability Should Be Considered Before DA Lodgement


One of the most expensive times to discover a design problem is after obtaining development approval.


By that stage, considerable time and money may already have been invested in the proposed layout.


Changing it may involve additional consultant work and, depending on the circumstances, modification of the consent.


Consider a five-townhouse development on a site with a noticeable crossfall.


The architectural concept achieves the intended yield and appears to satisfy the planning controls.


However, the proposed garage levels require extensive excavation, retaining walls and complicated drainage arrangements.


Those costs may not become clear until civil and structural engineering are developed.


If they weren't adequately considered during feasibility, the developer may face a significant increase in the construction budget.


A preliminary buildability review before DA lodgement could identify those issues while there is still an opportunity to adjust the design.


That doesn't mean completing every construction detail before seeking approval.


It means understanding the major construction risks before committing to a layout that may be expensive to change.


How Structural Design Affects Development Costs


Structural engineering has a direct influence on construction cost.


A building with straightforward load paths, regular spans and practical floor levels may be easier to construct than one with large cantilevers, complex structural transfers or numerous changes in level.


Sometimes these features are justified by the architectural outcome.


A large open-plan living area or elevated balcony may improve the market appeal of the finished townhouse.


But the developer should understand the cost of achieving those features.


If a design requires additional steelwork, substantial beams or complicated foundations, those costs need to be assessed against the value they create.


This is where early collaboration between the architect, structural engineer and construction team can be valuable.


The aim isn't to eliminate architectural features.


It's to avoid paying for unnecessary complexity.


Why Civil Engineering Should Influence the Site Layout


Civil engineering can affect the entire development, particularly on sloping or constrained sites.


Driveway gradients, stormwater drainage, on-site detention, sewer connections and retaining structures all need to work with the proposed building levels.


A driveway that appears suitable on an architectural concept may require substantial changes once the civil engineer assesses the gradients and vehicle transitions.


An existing sewer line may restrict where foundations or buildings can be positioned.


A stormwater detention system may require more space than initially anticipated.


These issues can affect the architectural layout and the construction budget.


When civil engineering is introduced late, the result may be redesign or additional construction work.


For property developers, resolving the major civil constraints during concept design is often more valuable than discovering them after approval.



Why Construction Details Matter to Developers


Developers don't need to design every structural connection or waterproofing detail themselves.


But they do need to understand the consequences of incomplete documentation.


Many building defects arise at interfaces between different materials and building elements.


Balconies, roof junctions, windows, wet areas and below-ground structures all require coordinated design.


For example, a balcony threshold needs to accommodate the structural arrangement, waterproofing system, drainage requirements and door installation.


If those details haven't been properly resolved, different trades may work from different assumptions.


That can result in rework, delays and potential defects.


Good construction documentation reduces uncertainty by establishing the intended construction method and performance requirements.


It also provides a clearer basis for tendering, contract administration and quality control.


What Happens Between DA Approval and Construction in NSW?


For developments proceeding through the Development Application pathway in NSW, obtaining development consent is generally followed by more detailed documentation and the relevant construction certification process.


A Construction Certificate is generally required before the applicable building work commences, together with satisfaction of other relevant pre-commencement requirements.


The Construction Certificate process assesses the relevant plans and specifications against applicable statutory requirements, including consistency with the development consent.


However, a Construction Certificate shouldn't be confused with a fully coordinated tender or construction package.


Certification addresses statutory requirements.


Construction documentation and coordination also need to address how the work will be priced, procured and delivered.


For eligible projects, a Complying Development Certificate provides a different pathway that combines planning and construction approval.


Developers should confirm the appropriate approval process and documentation requirements for their particular project.


Can Construction Drawings Differ From the Approved DA?


Construction drawings are expected to develop the approved design in greater detail.


However, they must remain consistent with the development consent and its conditions.


If detailed engineering identifies a change that is inconsistent with the approved plans, further assessment or modification of the consent may be necessary.


For example, a revised structural arrangement could affect the roof height, building dimensions or external appearance.


Even if the change improves buildability, it still needs to be considered against the approved development.


This can create additional design costs and delays.


The more significant the proposed change, the more important it is to understand the planning and certification implications before proceeding.



Why Incomplete Construction Drawings Lead to Tender Variations


Imagine issuing a townhouse development to three builders for tender.


The architectural plans are available, but some engineering details and specifications remain unresolved.


Each builder may approach those gaps differently.


One may include an allowance for additional retaining works.


Another may exclude them.


A third may price a different construction method.


The tender prices could vary considerably, even though all three builders appear to be pricing the same development.


This is why developers should be cautious about selecting a builder based solely on the lowest tender figure.


A proper tender assessment needs to examine the scope, exclusions, provisional sums, specifications and assumptions.


Where documentation is incomplete, the developer should understand which risks remain and how they will be managed under the proposed contract.


A lower initial price doesn't necessarily mean a lower final construction cost.


Tender Drawings vs Issued for Construction (IFC) Drawings


Tender drawings are issued to builders to obtain construction prices.


Issued for Construction drawings are authorised for use in carrying out the relevant work.


The two sets may not be identical.


Design changes, engineering coordination and tender clarifications can occur between pricing and construction.


If the IFC documentation requires work beyond what the builder priced, the difference may lead to a variation or another contractual issue, depending on the contract terms.


Developers should ensure the building contract clearly identifies the drawings, specifications and revisions that form the agreed scope.


Outstanding design items should be identified rather than left to assumptions.


An IFC stamp is a document-control status, not a substitute for statutory approval or professional design responsibility.


Why Drawing Revisions and RFIs Matter During Construction


Design coordination doesn't stop when construction begins.


An engineer may revise a footing detail.


The architect may update a window schedule.


A service connection may need adjustment following site investigation.


These changes must be communicated to the builder and relevant subcontractors.


A drawing register helps identify the current revision of each drawing.


Formal transmittals provide a record of when updated documents were issued.


Requests for Information, or RFIs, allow the builder to seek clarification where the drawings are unclear or additional information is required.


If a subcontractor constructs from a superseded drawing, the work may need to be corrected.


That can affect cost, programme and contractual responsibility.


For developers, effective document control is an important part of managing construction risk.



Value Engineering: Reduce Unnecessary Costs Before Approval


Value engineering isn't simply about choosing cheaper products.


It's about finding more efficient ways to achieve the intended design outcome.


A simpler roof arrangement may reduce complicated junctions and construction time.


A more regular structural layout may reduce the need for expensive transfers.


Adjusting floor levels may reduce excavation and retaining requirements.


Standardising selected building components may improve procurement efficiency.


These changes need to be assessed against planning requirements, building performance and market appeal.


The most valuable opportunities are often identified during concept design, when the project can still be adjusted without significant redesign.



After the construction contract is signed, they may also affect the contract price and programme.


When Should a Property Developer Engage a Builder?


For complex residential developments, early construction input can be valuable.


This doesn't necessarily mean appointing a builder under a construction contract before DA approval.


A preliminary buildability review or preconstruction consultation may be sufficient.


An experienced builder may identify difficult excavation, restricted site access, structural complexity or construction sequencing issues that aren't immediately apparent from the architectural concept.


Those observations can then be considered by the relevant design consultants.


The objective is to identify practical construction constraints before they become expensive problems.


Early builder involvement complements the work of architects and engineers.


It doesn't replace their professional responsibilities.


What Should Be Checked Before Signing a Construction Contract?


Before entering into a building contract, developers should understand exactly what is being priced.


The architectural drawings, engineering documentation, specifications and schedules should be reviewed for completeness and consistency.


Tender exclusions, provisional sums and outstanding design items need particular attention.


The contract should clearly identify the applicable drawings and revisions.


Where certain elements remain unresolved, the developer should understand the potential cost implications and the contractual arrangements for completing the design.


This is particularly important for specialist items such as retaining structures, waterproofing systems, façades and civil works.


A construction price is only reliable to the extent that the scope and underlying assumptions are understood.



OwnerDeveloper's Perspective: Design for Approval, but Think About Construction From Day One


At OwnerDeveloper, we consider property development design from both the development management and construction perspectives.


Planning approval establishes an important part of the development opportunity.


But the project still needs to be engineered, documented, priced and constructed.


From a development perspective, we consider the achievable dwelling yield, planning constraints, market demand and financial feasibility.


From a construction perspective, we consider the structural arrangement, civil works, construction methodology, access and the practical cost of delivering the design.


These considerations should influence one another throughout the project.


A development that achieves the maximum dwelling yield may not produce the best return if it requires excessive structural work or complicated construction methods.


Equally, reducing construction costs without considering the quality and marketability of the finished dwellings can undermine the development.


The objective is to achieve a design that satisfies the planning requirements, can be constructed efficiently and supports a commercially viable project.


Development approval tells you what you're permitted to build. Proper construction design helps determine how it will be delivered. Successful property development depends on getting both right.


Collage of property development team photos and award logos with text: From Planning & Approvals to Construction & Partnerships.

Frequently Asked Questions


What is the difference between DA drawings and construction drawings?

DA drawings primarily demonstrate the proposed development for planning assessment. Construction drawings provide more detailed architectural, engineering and specification information needed to build the project.


Are DA drawings enough to start construction?

Generally, no. DA drawings alone don't usually provide all the required technical information, and applicable certification and pre-commencement requirements must also be satisfied.


What is a Construction Certificate in NSW?

A Construction Certificate is a statutory certification confirming that the relevant construction plans and specifications satisfy applicable requirements, including consistency with the development consent.


What are IFC drawings?

Issued for Construction drawings are documents authorised for use in carrying out the relevant building work. They should reflect the current design and applicable approvals.


Why do construction costs increase after DA approval?

Detailed engineering and construction documentation may identify work that wasn't adequately allowed for during feasibility. Design changes, unresolved specifications and incomplete tender scopes can also affect costs.


Should value engineering happen before DA approval?

Major value engineering opportunities are generally best considered during concept design, when changes to the layout, structural approach and construction methodology can be incorporated more easily.


Disclaimer: OwnerDeveloper’s blogs are provided for general information and educational purposes only. They do not constitute financial, legal, tax, investment or other professional advice. Every property development involves unique circumstances and risks. Readers should seek independent advice from appropriately qualified professionals before making any investment, financial or development decision.



 
 
 

2 Comments

Rated 0 out of 5 stars.
No ratings yet

Add a rating
Guest
6 minutes ago
Rated 5 out of 5 stars.

Definitely worth reading for anyone considering their first property development. Getting the design right from the beginning could save a lot of money and headaches later.

Like

Guest
6 minutes ago
Rated 5 out of 5 stars.

Great article! I always assumed that once the DA was approved, the project was pretty much ready for construction. Clearly, there's a lot more involved.

Like
_M4_1154_1224x816_2664142.jpg

Get Daily Updates

Sign up for exclusive insights, expert opinions, project showcases, and the latest industry news!

Thanks for submitting!

bottom of page